![]()
    Updates and Information on upcoming events from the alumni association.
  MORE >>
  
  
  
From the PGPMAX Class of 2013
    
    Indian Electricity Sector - Overview
Electricity is the fulcrum of economic development in any country. India has installed power generation capacity of 210 GW as on November 30, 2012, which is about 154 times the installed capacity in 1947 (1362 MW). Electricity generation growth has been steadily improving year after year, and in the year 2011-12, the total electricity generation was about 876.8 billion units of energy with a growth of ~8% over the previous year. During the XI plan, the power sector made considerable progress with a capacity addition of ~58 GW which was significantly more than the capacity commissioned in the previous plans. Such an improvement in performance was possible mainly because of the strong private sector participation. However, India still faces the challenge of poor reliability and quality of electricity even leading to blackouts situation. Even as availability of power has increased substantially with significant investments on the supply side, the demand has consistently outstripped supply. India witnessed substantial energy and peak shortages of 8.5% and 11% respectively in the year 2011-12. The Indian power sector has been in a state of transition, from vertically integrated public utilities to unbundled entities, especially with more private participation on generation side. The changes have brought in improvement in efficiency and competition and offer opportunities with better price signals to incentivize the market participants across the value chain. Gaining confidence from these changes, India targets to set up substantially high ~88 GW of capacity in the XII plan which is also required to meet the growing demand. The XII plan target is definitely achievable; however, the sector needs to respond quickly and definitively to a number of new challenges that have emerged lately. These challenges continue to be both soft linked to policy as well as hard linked to project implementation. Some of the challenges can be resolved over time; however few critical challenges like the domestic fuel shortages, strengthening of transmission system, financially precarious condition of distribution utilities and the issues around competitive power procurement process needs to be immediately addressed.
Fuel Shortages
While most of the  constraints on the capacity addition appear to be subsiding, few new challenges  in the form of securing fuel supplies have emerged. Coal supplies declined on  account of lower production by CIL and also slow progress of captive coal  blocks which were allocated during past few years. These captive coal blocks  came under the scrutiny of the Comptroller and Auditor General of India (CAG)  and subsequently the Ministry deallocated~11 blocks in view of the  unsatisfactory progress in development of the coal mines and end-use plants.
    
    The uncertainty around  availability of domestic coal compelled IPPs to take stakes in international  mines for securing uninterrupted coal supply. However, the international coal  market has its own challenges in terms of lack of logistic support, changing  mining policies of coal rich countries and significantly high prices. Therefore  import of coal may be a good short-term strategy but is not a sustainable  option in the long-term. Indigenous coal production is required to grow at a  faster pace to cope up with the increasing demand from IPPs. Though, it may  take long for coal sector to be fully competitive, immediate actions are  required to support the power sector.
    
    Increased production of  natural gas with the commencement of production from KGD6 block during initial  period of XI plan attracted many private players to set up gas based capacity.  However, with reduced production of KG-D6, most of the existing capacity is  sitting idle. There is uncertainty on gas availability and production given the  slow pace of exploration in the upstream. Limited interest has been observed in  the recent NELP rounds primarily because of the gas pricing issue and the gas utilization  policy. It is clear that if the country wishes to secure more domestic gas  supply, producers will seek higher gas prices. The Rangarajan Committee has  suggested new gas pricing formula aligning producer prices to higher global  prices though the mechanics of how this will be done needs to be worked out. It  is expected that if accepted, this will lead to more domestic gas supplies.  Given the upward pressure even on domestic gas prices, the Indian power sector  needs to adjust to higher cost of generation from gas based power plants. The  policy framework needs to be developed to allow this relatively expensive gas  based generation to maintain the flexibility in grid operations which in turn  would lead to higher network reliability.
    
    Government has been also  exploring the pooled price approach both for coal and gas sector. While this  may help some stranded assets in the short term, it could have severe  implications on domestic production if continued for a long period of time.  Some of the reforms that could fast track fuel supply augmentation are as  follows: 
Transmission Congestion
Power despatch till date has not been a major problem on account of insufficient transmission infrastructure. However, given the aggressive plans of the private developers to set up generation capacities, the evacuation of power is likely to become a big bottleneck leading to stranded capacities. It is time we deliberate whether a highly planned approach for transmission sector can keep pace with the unbridled growth in the generation sector else like fuel sector, it may not be able to complement the growth in generation. The issues pertaining to Right of Way, environment and forest clearance, land acquisition etc. needs to be dealt with to enhance transmission capacity. An aggressive policy for the private sector participation in transmission sector needs to be formulated as has been implemented in the generation sector. Some of the reforms that could enhance system strengthening are as follows:
Financial Health of Distribution Utilities
The financial position  of the electricity distribution sector has been a concern for over a decade  now. The inability of the State-owned distribution utilities to remain  financially and commercially viable is putting at risk the significant  investments being pumped into the electricity sector by private and public  players. The accumulated loss of all State distribution utilities has been  estimated at Rs2.4 lakh crore as of March 31, 2012. In order to bail out the  ailing state utilities, the government announced the financial restructuring  plan. The scheme focuses attention on the short-term liabilities of discoms and  requires the State Government to take over 50 per cent of these liabilities in  the form of bonds duly guaranteed by it. Six states - Rajasthan, Uttar Pradesh,  Tamil Nadu, Andhra Pradesh, Haryana and Jharkhand have formally communicated  their agreement on the terms and conditions of the financial restructuring  package (FRP), including reduction of aggregate technical and commercial  (AT&C) losses and timely tariff revisions. The restructuring is expected to  bail out the power sector only temporarily but in the long term a number of  steps like functional autonomy of Discoms, reforms at the distribution level  and investments to augment capacity is required in addition to financial  re-engineering. With last one year as the exception, most of the states in India  did not revise their tariffs for many years  whereas their power purchase cost on account of fuel price kept on increasing  substantially leading to a growing gap between the operating costs and  revenues. Expectedly, many Discoms are finding them in financially precarious  situation with high financial losses and almost no cash left with them for  repayment of interest and principal. Post implementation of the FRP, if the  Discoms don't revise their tariff regularly and don't improve their operational  performance, they will again end up in a similar situation in the next few  years. Some of the suggestions that need
    to be considered by the  utilities, regulators and planners are-
To sum up, a difficult yet realizable roadmap lies ahead. If efforts are taken in right direction, India is poised for a faster, more inclusive and sustainable growth.
By
    Vikram  Tandon
    PGPMAX 2013